BIM Project: Intel Data Center Project

 


    Intel’s presence in Penang, Malaysia, has been a cornerstone of its global operations, particularly in the development and innovation of data center technologies. The Penang facility plays a pivotal role in Intel’s worldwide manufacturing, research, and engineering efforts, supporting cutting-edge advancements in cloud computing, artificial intelligence, and high-performance computing.


John Paul, played a crucial role in streamlining the Building Information Modeling (BIM) Interior Fit-Out process for Intel’s data center project in Penang. His expertise in BIM coordination and interior design optimization ensured a seamless execution of the workspace and facility upgrades, aligning with Intel’s high standards for efficiency, functionality, and innovation.



Key Contributions:

BIM Coordination & Clash Detection

Led the 3D modeling and clash detection process to identify and resolve conflicts between architectural, MEP (Mechanical, Electrical, Plumbing), and interior systems before construction, minimizing rework and delays.


Ensured compliance with Intel’s design and safety standards by integrating BIM with facility management requirements.


Space Planning & Layout Optimization

Developed detailed BIM models for interior fit-outs, including server rooms, office spaces, and collaborative work areas, optimizing space utilization for Intel’s operational needs.

Worked closely with architects, engineers, and contractors to ensure seamless integration of IT infrastructure within the interior design.


Material & Cost Efficiency

Utilized BIM for quantity take-offs and material scheduling, reducing waste and improving cost efficiency.

Provided real-time visualization for stakeholders, enabling better decision-making on finishes, furniture, and equipment placement.


Collaboration & Project Delivery

Facilitated multidisciplinary coordination between Intel’s project team, contractors, and vendors to ensure smooth execution.

Supported as-built documentation for future maintenance and facility management.

By leveraging BIM technology, John Paul Bocaya helped Intel’s Penang data center project achieve faster turnaround times, reduced construction risks, and enhanced design accuracy, ensuring a high-quality fit-out that meets Intel’s global standards.














Thursday, October 24, 2024

BIM Project: AMAALA Yacht Club - Red Sea Projects

AMAALA Yacht Club, KSA

JOHN PAUL VERANO BOCAYA
Scope of work and Task: BIM Lead Modelling
Company: DEPA Interiors LLC
Industry: Interior Fit-out
Developer By: Triple Bay Marina Yacht Club, Red Sea Project











Disclaimer: Images and Renders are Properties of Interior Designer and OCTA Properties. This Images are for Reference purpose only. This post is pertaining only to see the scope of works in parallel to the plans and scope of work of the owner of this blog site. All reference media is from the website link above.


Desert Rock Resort

Desert Rock Resort, KSA

JOHN PAUL VERANO BOCAYA
Scope of work and Task: BIM Modelling and Coordination
Company: DEPA Interiors LLC
Industry: Interior Fit-out
Developer By: Red Sea Project


Desert Rock Resort, Information (Website)










Disclaimer: Images and Renders are Properties of Interior Designer and OCTA Properties. This Images are for Reference purpose only. This post is pertaining only to see the scope of works in parallel to the plans and scope of work of the owner of this blog site. All reference media is from the website link above.


Moonstone Interiors By Missoni

Moonstone Interiors

JOHN PAUL VERANO BOCAYA
Scope of work and Task: SD | DD Stage Interior Design Plans
Company: House of OCTA
Industry: Interior Design
Interiors By: Missoni

Moonstone Project Details (Website)











Disclaimer: Images and Renders are Properties of Interior Designer and OCTA Properties. This Images are for Reference purpose only. This post is pertaining only to see the scope of works in parallel to the plans and scope of work of the owner of this blog site. All reference media is from the website link above.

Wednesday, October 23, 2024

La Mer Project

La Mer

JOHN PAUL VERANO BOCAYA
Scope of work and Task: SD | DD Stage Interior Design Plans
Company: House of OCTA
Industry: Interior Design
Lead Interior Designer: Elie Saab
Project Interior HOO: Patricia Balayao


La Mer Project Information (Website)










Disclaimer: Images and Renders are Properties of Interior Designer and OCTA Properties. This Images are for Reference purpose only. This post is pertaining only to see the scope of works in parallel to the plans and scope of work of the owner of this blog site. All reference media is from the website link above.